**Aggregator Development | 1 week** - Leaf database setup for aggregator server | 3 days - Connecting SMT aggregator to AB Root Chain | 5 days - Backup server setup | 1 day - Leaf database replication on backup server | 3 days - Automated fallback swap and service recovery | 3 days **Transaction Flow Implementation | 1 week** - Token split functionality | 1 week - Permissioned dust collection | 3 days - Verification of Unicity anchor connection | 3 days **GUI Development | 1 week** - Web GUI Token Manager | 1 week - Shell integration | TBD **Deployment & Launching Business Cases | 2 days**